Drip Edge Installation

 How to : Drip Edge Installation

1. Attach eave trim flashing to roof deck or purlins with 1 1/4” galvanized roofing nail 24” on center.

2. Install inside closures on the top edge of the drip edge flashing.

3. Overlap drip edge flashing a minimum of 3”

4. Allow drip edge to run past corner of roof 3” so it can be folded to ensure maximum weather

tightness.

5. Attach roofing panel at eave with a minimum #9 x 1 1/2 (1/4” magnetic bit) Woodgrip fastener

in the flat adjacent to each rib. (See fastener pattern on page 12)

6. Panel ends should hang past the eave 2”—3” or 1” for gutters.

* Purlin placement should be directly above fascia board along the eave line.

RECOMMENDED ACCESSORIES:

Inside Closures (1 closure = 3’ of coverage)